IESO Recommends Shift to Grid-Scale Storage in Ontario, Relying on Natural Gas Expansions to Ensure Reliability in the Near-Term

PB-61-IESO-logo-400.jpg

October 7, 2022

As part of its plans to acquire 4,000 MW of new electricity supply, the Independent Electricity System Operator (IESO) is recommending to the Minister of Energy that Ontario make a significant investment in battery storage, balanced by natural gas and other forms of non-greenhouse gas emitting generation to ensure reliability and affordability. This new capacity – enough to power a city the size of Toronto – is needed to support economic growth and electrification in the province.

“Our report sets out what is needed to maintain a reliable and affordable system as demand for electricity continues to grow year-over-year,” said Lesley Gallinger, President and CEO of the IESO. “These recommendations are designed to ensure that Ontario remains a magnet for businesses looking to invest while supporting communities as they push ahead with their decarbonization plans.”

The IESO’s Resource Eligibility Interim Report responds to a request from the Minister of Energy to provide recommendations on the eligibility of natural gas projects in ongoing IESO procurements for new electricity capacity. The report makes three key recommendations:

  • The IESO should move forward to procure approximately 2,500 MW of energy storage to provide flexibility to the power system, charging up when demand is low and providing electricity to the grid when it is needed most. Most of this new supply would be operational by 2027, representing what could be one of the largest storage fleets in North America.
  • These procurements should include other non-emitting forms of supply such as biofuels and renewable/storage hybrids – as they can also help meet peak demands and other changes in system needs.
  • In order to mitigate against global supply chain delays and ensure a reliable and affordable electricity system, up to 1,500 MW of natural gas capacity should be added between 2025 and 2027, in large part through upgrades and expansions at existing facilities.

“The IESO should tap into a diverse set of available options to meet projected electricity supply shortfalls mid-decade – including additional energy-efficiency programs and imports,” said Chuck Farmer, Vice-President, Planning, Conservation and Resource Adequacy. “This combined effort would ensure that the grid will be able to support a substantial energy storage fleet which will be essential for the decarbonization of the electricity system.”

The IESO’s recommendations are based on an assessment of the potential readiness of new projects to provide electricity capacity given current global supply chain and project development issues. Like other system operators, the IESO will build greater operational experience with batteries at grid scale while relying on additional natural gas capacity to ensure reliability when system conditions are strained.

Recommendations on the future role of natural gas will be included in the IESO’s Pathways to Decarbonization report to be released later this year.

Key Facts:

  • Ontario’s electricity system currently comprises approximately 38,000 MW of capacity, reflecting a diverse mix of supply options that includes nuclear, hydro, natural gas, wind and solar generation.
  • Ontario has one of the cleanest electricity systems in North America and emissions from electricity generation account for only three per cent of Ontario’s total emissions.
  • Demand for electricity is forecast to grow at 1.7 per cent annually over the next twenty years due to economic growth and decarbonization.

Pre-taped interviews with Lesley Gallinger and Chuck Farmer and b-roll of the IESO’s system control centre are available on request.

A copy of the report can be found on the IESO web site.

Source

Related Articles


Changing Scene

  • Tri-Mach Announces the Purchase of an Additional 45,000 sq ft. Facility

    Tri-Mach Announces the Purchase of an Additional 45,000 sq ft. Facility

    Recently, Tri-Mach Inc. was thrilled to announce the addition of a new 45,000 sq ft. facility. Located at 285 Union St., Elmira, ON, this facility expands Tri-Mach’s capabilities, allowing them to better serve the growing needs of their customers. Positioning for growth, this additional facility will allow Tri-Mach to continue taking on large-scale projects, enhance product performance testing, and provide equipment storage for their customers. Read More…

  • HELUKABEL Group Builds New Facility for Automation Cable Solutions

    HELUKABEL Group Builds New Facility for Automation Cable Solutions

    The HELUKABEL Group recently announced it is going to build a new facility in Haan, Germany that will house its robotic dress pack and drag chain system subsidiaries under one roof. The new building will also serve as the headquarters of HELUKABEL’s Rhine-Ruhr sales branch, and is planned to be completed by 2025. Robotec Systems’ core business is robotic dress pack solutions and has been a HELUKABEL subsidiary since 2012 operating out of Duisburg, a suburb of Duesseldorf in northwest Germany. Read More…


Sponsored Content
Fire Protection for Lithium-ion Battery Energy Storage Systems

Lithium-ion storage facilities contain high-energy batteries combined with highly flammable electrolytes. In addition, they are prone to quick ignition and explosion in a worst-case scenario. Such fires can have a significant financial impact on organizations. Rapid detection of electrolyte gas particles and extinguishing are the key to a successful fire protection concept. Since December 2019, Siemens has been offering a VdS-certified fire protection concept for stationary Li-ion battery storage systems.

Click HERE to learn more.


For a Multiplied Value Unified

PB-62-Excelpro-MultipliedValue-400.jpg

During the last few years, the Excelpro Group has welcomed AIA Automation, Envitech Automation and Conrad Lavoie Electrical, all of which have become ‘Member of the Excelpro Group’.

It was with great excitement that in November of 2022, Excelpro announced that these three companies officially became Excelpro. This decision is part of a strategy to enhance the Excelpro Group’s brand in its market.

These companies already collaborate on various client projects. This merger brings together the complementary strengths of the employees and ensures a global synergy of the activities throughout the Group.

Read More


Service Wire Co. Announces New Titles for Key Executives

Bruce Kesler and Mark Gatewood have been given new titles and responsibilities for Service Wire Co.

Bruce Kesler has assumed the role of Senior Director – Business Development. Bruce will be responsible for Service Wire’s largest strategic accounts and our growing Strategic Accounts Team.

Mark Gatewood has been promoted to the role of Vice President – Sales & Marketing. In this role, Gatewood will lead the efforts of Service Wire Company’s entire sales and marketing organization in all market verticals.

Read More


Modern Niagara Partners with Global Sustainability Platform Worldfavor

Worldfavor is a global sustainability platform, digitizing and automating the collection, calculation, aggregation and visualization for analysis and reporting of ESG data. Now, Worldfavor is proud to welcome Modern Niagara as a new customer. Modern Niagara is the first Canadian construction company to partner with Worldfavor.

“Worldfavor was founded to be the best platform for sharing, accessing and gaining insights from corporate ESG information. Worldfavor’s mission is to make sustainability mainstream and with that we offer solutions to accelerate sustainability through the value chain. Modern Niagara is the first Canadian construction company to partner with Worldfavor. 

Read More


JMP Parent Company, CONVERGIX Acquires AGR Automation, Expanding Global Reach

Convergix Automation Solutions has completed the acquisition of AGR Automation (“AGR”), a UK-based provider of custom, high-performance automation design and systems integration primarily to the life sciences industry.

Following Convergix’s acquisitions of JMP Solutions in August 2021 and Classic Design in February 2022, AGR marks the third investment in Crestview’s strategy to build Convergix into a diversified automation solutions provider targeting the global $500+ billion market, with a particular focus on the $70 billion global systems integration and connectivity segments. Financial terms of the transaction were not disclosed.

Read More


Latest Articles